Rolldown Process

INNOVATION EDGE™: ROLLDOWN PROCESS

The Rolldown process, used by Land & Marine Engineering Ltd, is a pipe insertion technique that maximises the diameter of the inserted pipe, while reducing carbon emissions and local environmental impact associated with traditional techniques.

Description

Rolldown is a site process that allows the installation of close-fit polyethylene (PE) liners into existing pressure pipelines. The intellectual property of the Rolldown is owned by Land & Marine, a wholly owned subsidiary of Murphy.

The machinery used in the process is provided by Subterra (Radius Systems).

The on-site process involves reducing the diameter of the PE pipes, inserting them into the existing pipelines, and reversing them to their original size. The dimensions of the PE pipes are specified so that their maximum external diameter is equal to the internal diameter of the existing pipeline.

The PE pipes can be welded together prior to processing. The pipe string is fed through a series of rollers, reducing the diameter of the pipe by around 10%. The reduction of the PE pipes is done at temperatures above 0°C. Approximately 1m of pipe can be reduced per minute.

The reduced diameter PE pipes are fed through the existing pipework using slipline insertion. The distance between the pipeline access points are dependent on the slipline machinery used, however insertions of typically 750m can be achieved. Once inserted, the ends of the pipe are sealed and water is introduced to the system. Water pressure within the pipe is slowly increased, causing the pipe to revert to its original diameter.

Benefits

  • The Rolldown technique maximises the diameter of the inserted pipe, using as much of the original pipe possible.
  • Unlike traditional open cut techniques, the Rolldown method does not require lengthy excavations. This leads to a number of significant benefits, including:
  • Avoiding disruption of local ecology, structures, roads and areas of historical interest.
  • Reducing excavation and its disposal to landfill, as well as purchase and delivery of infill materials.
  • It minimising the time spent on excavation and backfilling activities.
  • Reducing impact on businesses and stakeholders, including requirement for traffic control.
  • Decreasing hazards associated with trench digging (such as landslides and striking buried services).
  • The North American Society for Trenchless Technology (NASTT) suggests that in comparison to open trench method, the Rolldown process technique can achieve carbon emission savings of up to 95%. In addition, the PE pipes can be specified to either have full structural capability or rely on the structure of the original pipe.

Application

The Rolldown process was implemented by Land & Marine on a mains rehabilitation project for Bristol Water in Shipton Moyne, Gloucestershire. The £3.5m project involved the rehabilitation of approximately 19.5km of pipeline across private land and public highways.

During the project, the Rolldown process was utilised for 6.4km of the pipeline, with a traditional open cut technique used for the rest of the scheme. Pipes with 450mm external diameter were specified to sit inside the 18” (457mm) host pipe.

Excavation pits for the slipline insertion of the reduced PE pipes were located approximately every 150m, reducing the impact on the local environment.

An A-road, along with various areas of archaeological interest and numerous waterways were located above the existing pipelines. The subtleness of the Rolldown process ensured that these areas were not affected by the rehabilitation works.

End user feedback

It was found that manipulation of the pipes in higher temperatures was considerably easier. The process has limitations at temperatures below 0°C.

“The Rolldown method allowed us to avoid areas of environmental interest, and reduce the impact to the local residents and land owners” – Mike Baker, site foreman at Land & Marine.
 
Market potential

The Rolldown process can be used for most pipeline rehabilitation projects, when undertaken in temperatures above 0°C. The technique is suitable for water, gas and sewer pipelines, however it can only be used on pipes made from PE.

Learn more

For more information, please contact Murphy marketing & communications department at communications@murphygroup.co.uk

Latest Stories

  • 25th Oct 2017

    Murphy awards first-class engineers... Read More

  • 25th Oct 2017

    Murphy work with IOP and Met Police to reach out on cycle safety... Read More

  • 24th Oct 2017

    Murphy to the rescue – the trilogy... Read More

View All News